At about 10:00 we went to the field to the site at STA 18+200 to see construction of left side ditch. We found that the ditch was reinforced to a layer. The ditch floor had been casted. We then when to Parungkuda Gate to observe the construction of the office. At about 11:00 a team from Protocol section of Ministry of Public Works and Housings came to survey the site for project operation inauguration. We stood by for their question.
At Edli called us to join Subteam 1 in Ramp4. Subteam 1 would monitor the TJT follow ups of the their findings during functioning feasibility test. The team consisted of AKBP (Police Deputy Grand Commissioner) Sulaeman and Bripda (Police Second Brigadier) Bima Setiawan from Indonesia Police, Vircan Yuana, Akhmad Bustomi, and Mahirdi Lingga, from DG Land Transportation. I and Yonrizal accompanied the team. We inspected all the finding locations on track A (Cigombong to Parungkuda). Amid the inspection we had lunch at Pak Atok Ciutara Roasted Chicken in Nyangkowek Cicurug, Sukabumi Regency.
After having lunch the traced the track B (Parungkuda to Cigombong). We ended at Ramp3. We then went to TJT office to wrap the findings. The wrapping was finalized after isha time. At 19:00 Agus the leader left the office for Bogor accompanied by Herry and Ipang. I and Yonrizal were still at the office. Bayu insisted us to stay since the dinner boxes for us were ongoing to come.
At 19:30 I and Yonrizal along with Abdul Salim left TJT office. Yonrizal got off at his guesthouse in Nanggerang. Because the national road was congested I used toll road to achieve Cigombong. I asked Alim to clear the exit point. He told we could exited at Ramp3.
Tidak ada komentar:
Posting Komentar