At 09:10 I walked to the office. There were Agus, Herry, Nanang, and Yusuf there. We were ready to join a meeting in TJT office. At 9:50 we went there.
As usual the meeting started in delay because of the late coming of contractor team. At 10:27 the chairman Mr. Joko Susilo the project manager opened the meeting. He was with Edli and Tavip on his side. He welcomed the Directorate General of Roads team that consisted of Dimas Sri Wicaksono, Nanang Hidayat Aziz and Susilawati. The last 2 people were consultants for DJoR. The other attendants were us from Eskapindo Matra the supervision consultant that consisted of Agus, Endang, Yusuf, dan Entis. From the other parties were Iksan from Wahana the internal quality control consultant and Alim and Yogi from Waskita Karya Infrastructure the contractor. The meeting was to facilitate the DJoR team to monitor the project team (TJT, contractor, supervision consultant, and internal quality control consultant) on fixing or finalizing findings during functioning feasibility test (ULF).
After we agreed with the steps of monitoring we stopped temporarily to give time for us to pray and to have lunch. We went to a resto named Ayam Bakar Pak Atok Ciutara in Nyangkowek Cicurug, Sukabumi Regency. Mr. Joko served us lunch. We tasted ayam bakar (baked chicken), fried carp in chilli souce, and fried carp in banana souce.
At 13:30 we started inspection from Parungkuda intersection. We went up to the smaller STA. At 17:00 we finalized the inspection and together went to TJT office again to compile the findings. Mr. Joko served us with dinner box. I did not had it because I would dine in the guesthouse.
After isha time we together watched the findings one after another. The findings were compiled in 27 sheets. At 22:00 the watching finalized. At 22:17 we dismissed after some of us gave the signatures. I and Herry went back to the guesthouse. Abdul Salim got us there.