At 11:30 I along with Abdul Salim went to Cibunar Jaya OP. We found DS-5 at left approach had been installed. Weeds are growing inside. On the way back to the office we stopped by at Maranti food stahl for having lunch.
At 14:00 I joined weekly meeting in Trans Jabar Toll (TJT) office. The meeting was chaired by Mr. Joko Susilo the project manager. The TJT participants were Edli, Tavip, Bayu, Satriyo. The Waskita Karya participants were Irawan, Alim Tri Astowo, and Arviantoro. The Eskapindo Matra participants were Agus Pranoto, Endang Gunawan, Yonrizal, Herry Firdaus, and Toni. The chairman told at (1) 14 Juni TJT would apply ULF (Functional Feasibility Examination) to DG of Road. (2) time was run out to get PHO partial 1 so the scope would be shorter. (3) side ditches had to be finalized. (4) monitor progress by displaying the last minutes of meeting. The meeting concluded at 17:15.